Bachelors Level/Fourth Year/Seventh Semester/Science bit/seventh semester/software project management/syllabus wise questions

Bachelors In Information Technology

Institute of Science and Technology, TU

Software Project Management (BIT402)

Year Asked: Model, syllabus wise question

Activity Planning
1.
What is critical activity and critical path? Explain network diagram with a suitable example. [10]
Introduction to Software Project Management
1.
How can you differentiate software projects and other types of projects? [5]
2.
Highlight on different activities that needs to be carried out in project management. [5]
Managing Contracts
1.
What is contract? Explain its different types. [5]
Managing People in Software Environments and working in teams
1.
What is the importance of leadership? Explain. [5]
Monitoring and Control
1.
What is the significance of earned value analysis? Explain. [5]
Project Evaluation and Program Management
1.
Explain the importance of cost benefit analysis. What are different values that are calculated while performing cost benefit analysis? [5]
Risk Management and Resource Allocation
1.
List different risk items. How can the risk exposure value help in handling risk? [5]
Selection of an Appropriate Project Approach
1.
Differentiate between Extreme programming and prototyping. When do you think extreme programming can be used? [10]
2.
Write short notes on a. Change management b. Scrum [5]
Software Effort Estimation
1.
Explain any one cost estimation technique with required equations. [10]
Software Quality and Project Closeout
1.
How can the quality of software be enhanced? Explain. [5]