Section A

Long Answers Questions

Attempt any TWO questions.
[2*10=20]
1.
What is critical activity and critical path? Explain network diagram with a suitable example.[10]
2.
Explain any one cost estimation technique with required equations.[10]
3.
Differentiate between Extreme programming and prototyping. When do you think extreme programming can be used?[10]
Section B

Short Answers Questions

Attempt any Eight questions.
[8*5=40]
4.
List different risk items. How can the risk exposure value help in handling risk? [5]
5.
How can you differentiate software projects and other types of projects? [5]
6.
Explain the importance of cost benefit analysis. What are different values that are calculated while performing cost benefit analysis? [5]
7.
How can the quality of software be enhanced? Explain. [5]
8.
What is the importance of leadership? Explain. [5]
9.
Highlight on different activities that needs to be carried out in project management. [5]
10.
What is the significance of earned value analysis? Explain. [5]
11.
What is contract? Explain its different types. [5]
12.
Write short notes on a. Change management b. Scrum [5]